Paul,
I just ordered the 89 rotor housing so when it gets here I will send them
plus the sealing plates for P Porting. Â How many housings do you have so
far?
Joe Berki
Limo EZ
We have six. Yours will be eight and somebody said they would send three
more.
Paul Lamar
I got to figure out how to take it apart. Then I will send mine.
Blake
--
Blake C. Lewis
I assume you have the shop manuals. One mistake frequently made is to take the flywheel
off first. The screw holding the pulley on the front of the engine should be removed
first. The flywheel must be immobilized to get the screw off the front of the e-shaft.
I at first tried an angle iron and bent it. I then got a 3 inch channelsix foot long.
The right tools are important. You will need a 2-1/8" 54 mm socket and you will need a
3/4 inch breaker bar with a 6 foot extension or a good 3/4 drive impactwrench. Harbor
freight is a good source as you won't be using these things that often.You will also
need a 5 pound sledge hammer minimum. Assuming of course you have a manual transmission
engine.
If not a manual you will need a special gear puller than can be made orbought from
Mears Motors. Once you get the screw off the front and the flywheel or counter weight
off the e-shaft the rest is trivial and can be done in less than 5 minutes.
It will take a day to clean the rotors each so I would farm them out toan automotive
machine shop and get a quote ahead of time because they don't know whatthey are getting
into :)
Paul Lamar
You should recieve my housings tomorrow(UPS)
sounds like we are getting close to a run on the mill
Geir
We may have enough all at once to do 11 or 13.
On Friday I'll set a dead line of one week later to collect the
stragglers :) Get those rotor housings in folks. It will be quite some
time before we do another batch.
Paul Lamar
--